Sheetflow Construction Erosion and Sediment Control

October 29, 2019

Open Catch Basin Open Again

Filed under: Photo — Tags: , , , , , , — Sheetflow @ 4:55 am
Why, this was flooded yesterday, what happened? Photo: David Jenkins

The saga continues… the next inspection looked like the first inspection. 500 + NTU water draining into the catch basin. What happened?

30 mil PVC punctured to let water drain. Photo: David Jenkins

As suspected, someone didn’t like the flooding, so they punctured the 30 mil PVC. I am wondering why the contractor erosion control lead is not finding this.

October 4, 2019

Broken Waterline

Broken 16 inch waterline. Fortunately, all of the muddy water was contained in a 72″ storm pipe with a valve. Water was then pumped to a Chitosan-enhanced Sand Filtration (CESF) system for treatment to 5 NTUs for discharge to a creek. Knowing this project was going to be constructed over several winter seasons, we specified the CESF system in the contract.
Photo: David Jenkins