June 16, 2016

Paying for TESC

The Best Way to Measure and Pay for TESC in Public Works Contracts

It is a big mistake to make temporary erosion and sediment an “incidental” item in a public works contract. Anything that can be measured should be and set up as a Unit Price item. Planning and Implementation can be lump sum but measurement and payment must be clearly specified. Force Account is set up for unforeseen conditions; the amount is set by the owner so that everyone bids the same number. Make clear at the pre-bid meeting that the Lump Sum bid for planning and implementation covers lots of stuff and they need to bid accordingly. Here is an example of the best way to pay: (more…)