Sheet Flow Construction Erosion Control

November 30, 2020

Compost Socks

Filed under: Power Point — Tags: , , , , — Sheetflow @ 1:53 am

As I have written in previous posts, compost socks make excellent perimeter berms, especially when used on impervious surfaces. Make sure to overlap the ends and don’t drive over them. Recycle the compost when done.

Presentation: David Jenkins
Presentation: David Jenkins

July 29, 2020

Install Compost Socks

Photo: David Jenkins

Install Compost socks with an overlap on each end to maintain a continuous berm. 8 to 12 inches works well. Consider this when figuring out how many you need to order.

September 24, 2020

Biodegradable Erosion Control BMPs: Burlap Fence Compost Sock

Video: David Jenkins

Biodegradable Erosion Control BMPs: Burlap Fence Compost Sock

My goal was 100% biodegradable BMPs on this habitat restoration project. In this video I show the burlap silt fence and the compost socks.

September 1, 2020

Compost Sock Damage

Photo: David Jenkins

Compost socks won’t take hard use. Constant movement and driving on them tears them up so they should be used in areas that don’t get much traffic or at the base of fence and jersey barriers.

November 10, 2020

What’s Wrong with this Photo?

Photo: David Jenkins-Sheetflow Erosion Control

What’s wrong with this photo? On first glance, it looks like a peaceful pathway across a stormwater swale. In reality, it is two compost socks that need to be overlapped and one burlap silt fence that needs maintenance.

September 21, 2020

Steel Plate Construction Access

Video: David Jenkins

This is a steel plate construction access that we built across a live stormwater swale. We have installed compost socks along the edge to keep construction runoff out of the swale.

August 24, 2020

Construction Access with Steel Plates

We built a construction access with steel plates across this stormwater swale. Then we laid compost socks and straw wattles along side of the eco blocks placed along the edges.

The adjacent parking lot drains into the swale and must be protected from dirty construction stormwater discharges.

August 17, 2020

Adaptive Management-Perimeter BMPs

There is a difference between the paper erosion plan and what the project looks like in the field. I wrote up the plan to manage water from offsite. Now that I am looking at the area, I might need to re-think the plan. Erosion control adaptive management is what makes the plan come to fruition. Video: David Jenkins-Sheetflow

This video gives an example of adaptive management for perimeter erosion control BMPs.

Transcript:

This is our staging area for our project we are going to be starting up back over in here on the other side of a stormwater swale. We have to access the site through another owner’s property and they have allowed us to have this staging area.

My plan was to have an extruded asphalt curb along this edge to take all the stormwater running off the parking lot coming this way and keep it out of the staging area, but that’s going to concentrate all the water from back up to the left into one location there down by the equipment.

Another BMP we’re using is compost socks on the edge of the swale to take any sheet flow from the staging area here and spread it out before it goes into the swale. Here are the compost socks and a bunch more here waiting for installation.

The idea of concentrating all the water and dumping it into the swale in one spot down here, maybe its better with the compost sock to just let everything just sheet flow and spread out against the sock and then dribble in, and actually in this area its not going right into the swale its going into some landscape across the pathway and then into the swale so maybe it’s a combination.

Actually, come to think of it, maybe on this end of the project no curbing and back over in here we put curbing in. This is all pretty protected so you know, this is adaptive management, this is how these things go you do the erosion plan write it up on a plan sheet and then you walk the site and see how things are in reality and should be willing to change.

Okay from here now from this pathway over we are going right into the swale so maybe we start the curbing maybe off this island. You see were gong into the swale now and this is going to be the most intensively used area for staging so maybe we start with a short, extruded asphalt curb over there and let everything else sheetflow back in here.

Okay got to think on this.