Whenever I see something like this, it makes me think that the site owner/contractor either didn’t know what they were doing or bit off more project than they could chew, or both. These guys cleared, grubbed and graded something over 80 acres starting in late summer, failed to phase the work, failed to use soil cover practices, failed to listen to the experts and got nailed by the fall rains.

Erosion control is really about water control: reducing volume, preventing it from becoming turbid, and controlling where it goes. By the time the rains hit this project, there was too much water, it was too dirty, and there were too few options for controlling where it went.

In addition, they refused to set up a chitosan-enhanced sand filtration system to treat and discharge water; this left them no options and too much turbid water that had nowhere to go. As a result, they hammered a wetland, were fined heavily, and were shut down for months.

Silt fences are not meant to control water, convey water, filter water; they are designed to control eroded sediment. Ditches, berms (rock, gravel, triangular silt dikes, etc.) would have been better choices at this location. Not opening up so much area so late in the season would have been the best option. Their means and methods did not save them time or money.

No Comments

No comments yet.

RSS feed for comments on this post.

Sorry, the comment form is closed at this time.

Powered by WordPress